fbpx
News

Parts of FCT to suffer power outage as TCN announces maintenance

The Transmission Company of Nigeria (TCN) wishes to inform the public that its engineers will carry out a planned maintenance on a 33kV feeder at the Kukwaba 132/33kV Transmission Substation, Abuja.

This is to enable TCN engineers install a new 33kV disconnector on the L31 line bay.

The maintenance is scheduled for Thursday, 24th October 2024, from 9am to 6pm. During the period, only one 60MVA power transformer will be out of bulk power supply for nine hours.

Consequently, Abuja Distribution Company (DisCo) will be unable to offtake bulk power from the affected 60MVA power transformer for onward distribution to its customers in Galadima, Kabusa, Sunnyvale, Suncity Estate, Wonderland, Human Right Radio, Brilla FM, Kubusa Garden Estate, Jewel Apartment and environs.

TCN apologises for any inconvenience this may cause electricity consumers in the affected areas and notes that adherence to power equipment maintenance is essential for optimal performance.

Ndidi Mbah
GM, Public Affairs
23/10/2024

Back to top button

Discover more from Dateline Nigeria

Subscribe now to keep reading and get access to the full archive.

Continue reading