The Federal Government says it is adopting holistic approach in addressing reoccurring incidents of grid collapse in the power sector
The assurance is coming from the Minister of Power, Adebayo Adelabu as the investigative committee on frequent incidents of grid collapse submits its report.
The short term recommendations are expected to be implemented within the next six months to stabilize the grid.
The Transmission Company of Nigeria (TCN) had earlier in a statment said the most recent collapse was caused by a sudden rise in frequency from 50.33Hz to 51.44Hz.
“The frequency spike was caused by issues encountered at one of TCN’s substations, which had to be shut down to prevent further complications.
“In addition to this, TCN is actively engaged in significant repair work on several critical transmission lines and substations. This includes the 330kV transmission line along the Shiroro–Mando axis, major upgrades at the Jebba Transmission Substation, and the restoration of the second Ugwuaji–Apir 330kV transmission line.
“Furthermore, following the submission of the investigative report on the causes of previous grid collapses, TCN has begun addressing the identified weaknesses in the transmission system.
“Efforts are being made to close the gaps highlighted in the report, and to enhance the overall stability and resilience of the grid. These efforts include both technical upgrades and strategic interventions based on the committee’s recommendations.
“However, it is important to note that while these repairs and improvements are underway, some degree of instability in the system is likely to persist until all major works are completed. TCN acknowledges the impact of these disruptions and kindly asks for the understanding and patience of the public during this challenging period.
“The company remains committed to improving the reliability of electricity supply, recognizing the vital role that stable power plays in Nigeria’s socio-economic development.
“TCN assures the public that all necessary measures are being taken to ensure the grid’s long-term stability, in line with the recommendations of the investigative committee, while also addressing infrastructure damage such as vandalized transmission lines, TCN’s General Manager, Public Affairs, Ndidi Mbah, said in the statement.