NNPC signs $1.5bn contract for PH refinery rehabilitation

  • To award Warri, Kaduna refineries rehabilitation contracts in June

The Nigerian National Petroleum Corporation (NNPC), on Tuesday, signed the Engineering, Procurement, Construction, Installation and Commissioning (EPCIC) contract for the rehabilitation of the 210,000 barrels per day capacity Port Harcourt Refinery in Alesa-Eleme, Rivers State.

The rehabilitation project which has a completion timeline of between 18 and 44 months under a three-phase arrangement was awarded to Milan based Tecnimont SpA at $1.5 billion, inclusive of VAT and other statutory payments.

Read Also: Gunmen attack another police station in Imo, free detainees

The Group Managing Director of the NNPC, Mallam Mele Kyari, said the PHRC rehabilitation project was in line with President Muhammadu Buhari’s promise to the Nigerian people to make the refineries work.

Mallam Kyari reiterated that in arriving at the choice of Tecnimont SpA, the Corporation embarked on a transparent tender process which can withstand any forensic audit, noting that NNPC was ready and open to answer any question pertaining to the project.

He assured that the same transparent process has been emplaced for the rehabilitation of the Warri and Kaduna Refineries whose EPCIC contracts would be awarded in June 2021.

The GMD explained that the rehabilitation exercise was very different from a routine Turn-Around Maintenance as it would entail a total retrofitting of the plant with major part and equipment replaced with new ones.

Providing further insight into the project, Managing Director of Port Harcourt Refining Company Limited, Engr. Ahmed Dikko, explained that Phases 1 and 2 of the project would get the refinery ready to receive hydrocarbon, while Phase 3 will focus on the start-up the refinery for operation, stressing that the entire work shall be delivered in 44 months from today.

In his remarks, Vice President, Sub-Saharan Africa Region of Tecnimont SpA, Davide Pelizzola, pledged the readiness of his company to work assiduously with the NNPC to comply with the terms and obligations of the contract.

The signing ceremony of the PHRC rehabilitation project was witnessed by the Nigeria Extractive Industries Transparency Initiative (NEITI), Infrastructure Concession Regulatory Commission (ICRC), Petroleum and Natural Gas Senior Staff Association of Nigeria (PENGASSAN) and the Nigeria Union of Petroleum and Natural Gas Workers NUPENG amongst others.